Construction of the Stahl Road storm sewer started in August after ten years of planning for the project. We bid the project in May and received 6 bidder for the construction. The contract was awarded to S & S Builders and Excavating. The project should be finished in mid-September. The project includes the installation of 954 feet of 36 inch pipe, 1523 feet of 30 inch pipe and 8 catch basins. The project should be finished in mid-September. This is one of four major storm sewer projects Ballville Township have completed in the past two years.